How To: Add Progress Lines in MS Project

Progress lines in Microsoft Project help see where tasks are behind schedule.  They’re hideous to look at, but serve a useful purpose.  This post shows how to add progress lines to a Microsoft Project file.  Buckle up; this may get rough.  🙂

 

Start by adding a few tasks to a new project:

  1. Add Task 1, with 10 hours duration
  2. Add Task 2, with 20 hours
  3. Add Task 3, with 30 hours

The tasks and Gantt bar should look like this.  At this point, we have no progress lines, just simple task bars in the Gantt chart.

 

 

Add a Project Status date:

  1. Choose Project, Project Information
  2. Enter a ‘Status date’ for when you would like to check task status (the status date progress line will be red)
  3. Click OK

 

Add progress lines:

  1. Choose Tools, Tracking, Progress Lines
  2. Click ‘Always display current progress line’
  3. Click ‘At project status date’
  4. Click ‘Display selected progress lines’
  5. Click in the list and choose the dropdown arrow
  6. Select a date for a progress line (these lines will be black)
  7. Click OK

You should now have two progress lines on your Gantt chart, and things may have gotten a little ugly.  As you move the task bars, the progress lines will update.  Tasks before the progress line will cause the line to go leftward (that’s the ugly part).  What good are they?  Backward facing lines are those tasks you need to move forward.  They need to be rearranged to meet your current project plan.  The image below is an example.  Notice how the lines go backwards to tasks that are behind schedule.

 

 

–ray

Sleeping on the Job

Sleep happens!  Especially on Mondays…  I recently read that 35% of all respondents to a recent polls admitted to napping on the job.  If I would have taken the poll, what do you think I would have said?

Of course I have!  And the other 65% have too, but they won’t admit it.  I’m not sawing logs all day long, but yes, it happens.

The MSN article below claims we’re sleeping about 2-3 hours less than those before the invention of the electric light bulb.  Duhh.  That’s no surprise.  Every invention has its unintended consequences.

http://health.msn.com/health-topics/articlepage.aspx?cp-documentid=100205002>1=31036

I really feel this has an effect on our projects.  I remember burning the midnight oil during the dot com, while attempting to start a new software company.  I literally worked two back-to-back 8-hour days.  And fought to stay awake every day.

Most people don’t go to that extreme, but they do watch their shows, surf the web, and play video games late into the night.  All because of the humble electric lightbulb.  🙂

 

–ray

Analysis Paralysis Strikes Again!

I thought I was done with this subject last week.  But then it struck again, Analysis Paralysis!  I am near completion of a deal that is over 4 years in the making, not for me, but for a fortune 100 company.  In other words, they’ve been work it this long.

This company has been looking for a solution and had contacted one of our reps back in 2003.  They were about to move forward with the implementation but someone convinced them to wait, and ultimately pushed to build the program in-house.  It’s the same story I hear time and again, “we can build it in-house for half the cost”.

Yeah, right.

So here I am in a conference call with a handful of representatives from this large company and they are sharing with me how after 4+ years they couldn’t build a good tool and wanted to use ours.  This happened for a number of reasons.  Reason #1…It’s not what they do!  Sure it looks easy, but when you actually set out to do it, reality hits.  Reason #2…not enough time.  Building a tool takes away from their core business, and that always takes a back seat.

Suppose I wanted a nice wooden baseball bat and I see that Louisville Sluggers cost $29.  If I’m not careful I could be talked into buying a piece of lumber, sticking it on a wooden lathe and saving myself ten bucks to make my own.  We all know that would be a disaster. Yet somehow in business we don’t always take that same common-sense approach.  Instead we waste too much time arguing, waiting and losing money.  Isn’t it better to pay a small premium for another’s well invested expertise?

Waiting usually costs more than doing nothing or delay.  As one CEO recently said, “After hearing all the facts, make a confident decision, even if you aren’t certain.  It’s indecision that is costly”. 

 

–Warren

Define: Work Variance

Work Variance: Difference between the current ‘Work’ value and the baseline ‘Work’ value for a task .  In Microsoft Project, this is a read-only column.

 

There are a lot of variance fields in Microsoft Project, and they all relate to baselines.  Baselines are a way to compare your current values with original estimates.  A baseline captures all task values, including ‘Work.’  Weeks or months after capturing a baseline, you can compare those original estimates with current numbers.

To save a baseline in Microsoft Project, choose Tools, Tracking, Save Baseline.  To view all the baseline values, choose View, Table, Variance.  This changes the columns in the current view to show variances to the baseline.

 

–ray

Six Sins of Consulting

Biblically, 7 is the number of perfection, and 6 is the number of “man.”  Remember 666, the “number” of the Antichrist?  In light of that, I’m going to enumerate the worst sins consulting companies can make.  These are the ones that doom them to hell on earth.  If you’ve been in business for any length of time, you have probably already nailed these and gotten past them.  But they may be worth reviewing.

#1: Ignoring your customer’s complaints
The customer is always right, right?  No, not true.  But, when they believe they are right, you had better be there to work things out.  Sometimes you can make them see your position in a disagreement, but more times than not, you’ll need to suck carpet and make things right.  That’s part of what they expect of the relationship.  The mere fact that you take money from them puts you in that position.  Cruel fact of life – get used to it.

#2: Failure to smooze
This one is akin to the first, but slightly more on the positive side.  Remember the old adage “out of sight, out of mind?”  That’s what happens when you haven’t had face-time with your customer in a while.  They literally think less of you.  The relationship grows cold and they are less likely to call on you when a need arises.

#3: Letting sales slip
Consultants and consultancies have two big jobs: consult and sell consulting services.  Both are equally important.  Once a gig has been landed, the tendency is to settle in and forget about what comes next.  Looking for the next gig is hard.  It’s much easier to do what you’re competent at, and let the sales work take care of itself.  Problem is…  it often doesn’t.  When the gig ends, you’re on the street again without work.

#4: Shoddy work
This one’s so obvious, it’s hardly worth mentioning.  But it really goes deep down to the type of person you are.  Keep your standards high.  Remember that you are competing with other consultants, and for future work.

#5: Low utilization
Got a nice high billing rate?  Higher than working at Wal-mart?  Consider this: your “effective” billing rate (or utilization rate) is your revenue divided by the total calendar hours.  For example, $50,000 divided by 2,000 possible billable hours in a year is an “effective” rate of only $25 per hour.  You may charge $100 and hour for your time, but only book 25% of the total possible hours.

#6: Not picking up the scraps
Nobody likes to think of themselves as a handyman who takes odd jobs.  We’re skilled professionals with higher education.  But there’s no shame in stooping down to pick up small jobs.  Sometimes you can even charge more for them.  They can fill gaps between the big gigs and give you interesting new experiences.

 

–ray

How To: Show Critical Path Tasks

Here, we’ll be showing how to display critical path tasks in Microsoft Project.  The critical path is the sequence of tasks that take the longest to reach the project goal.  The steps below can be used to display your project’s critical path.  Follow these, and you’ll know which tasks threaten the final completion date of the project.   Create tasks to display the critical path: Enter three tasks Make the second task twice as long (in duration) as the first task Link the first task to the last task Link the second task to the last task At this point, the tasks should look like this.  Both the first and second tasks link to the last one. Two tasks, links to final task   Group the tasks by critical path: Choose Project, Group By, Critical Or, choose ‘Critical’ from the ‘Group By’ dropdown in the toobar After choosing this menu item the tasks will be grouped differently.  All the tasks that are not in the critical path will be displayed first (in the in ‘Critical: No’ group).  All the tasks in the critical path will be in the second group (‘Critical: Yes’). Tasks grouped by ‘Critical’   Format the Gantt column: Right-click in the Gantt column Choose Gantt Chart Wizard Click Next Click the ‘Critical path’ option Click Finish Click Format It Click Edit Wizard After formatting the Gantt column, the task bars in the critical path will turn red. Critical path task bars are red   –ray

When Projects Get Killed

This is a follow-up to the post named “Why IT Projects Get Killed.”  I began to wonder at what stage IT projects get killed.  In other words, when they are canceled.  Most of the projects I’ve worked on have been successful, but I’ve seen my fair share of canceled projects.

For this post, I decided to take a guess at when I felt IT projects are canned.  Of all the canceled projects, these are my guesses at when they occur.  I have no detailed surveys to back up my assertions, just a little experience.  So, here goes…  Post a comment and let me know what you think.

    25% In the investigative stages
    50% In the requirements gathering stage
    10% In the development stage
    10% In the final QA stage
    5% In the pre-sales marketing stage

25% In the investigative stages
This one’s fairly obvious.  A project passes the “good idea” stage and passes into the “due diligence” stage to learn its true value.  That’s when it dies.  Not all good ideas have true merit, or can be marketed effectively with the given resources.  It’s common for projects to die here.

50% In the requirements gathering stage
Here, the project members are interviewing customers and collecting information.  They may even be building prototypes to prove the concept.  But just as in the investigative stages, the idea may die because it cannot meet requirements or marketing expectations.  Again, lots of possible reasons for cancelation, but most of these are because the idea wasn’t feasible.

10% In the development stage
By the time it’s gotten to the stage where development resources are committed, it’s probably proven to be viable or too highly visibility to cancel.  By this stage, the project stakeholders may never cancel it, even if it isn’t viable.  Egos and persistence are at play here.

10% In the final QA stage
Sometimes products never meet customer expectations, or will cost too much to do so.  The project may have gone terribly over budget, and customers hate it.

5% In the pre-sales marketing stage
Surprisingly, some get to this last stage, and still die.  I was once involved in such a project in 1995.  It was killed after two years of intense development, before a single sale was made.  That’s right!  We finished a two-year death march, only to find the product pulled from marketing.  There were too many competitors and not enough customer value.  That fiasco, and a few others like it, eventually killed the entire company.

 

–ray

Analysis Paralysis

We’ve all heard the term analysis paralysis, and frankly it is a millstone around the necks of many corporations, especially ones that are heavily layered in management.  In today’s world economy only the quick and flexible survive. 

Imagine you have a great idea you spend days, if not weeks, researching.  You run the initial numbers and cost analysis that shows a marked improvement with a bottom line benefit.  You can hardly contain your excitement!!  So, let’s get started, right? Wrong!

Bob, over in development, isn’t sure this will actually save the company money and he thinks they “might” be able to build their own tool.  So he talks to Chris in accounting and before you know it there are too many cooks in the kitchen and everything is on hold!

It took 6 months before a decision was made to build this tool in-house.  It took Bob’s team over a year to figure out they couldn’t build the tool properly, and they spent 12 times the amount the original “off the shelf” implementation would have cost!  And the final result?  Still waiting…

If they had simply gone with the original idea of an off the shelf tool they would have saved the company enough money to buy the thing 20 times over!  Instead they’re back at square one.

I am all about due process and thinking things through.  However, at some point a decision must be made and all too often one isn’t made out of fear, job security, or simply because someone is being territorial.

This is a common story and that’s why strong leadership is important.  If you’ve done the homework and you know it’s a worthy endeavor… push, push and push some more.  In the end you will be rewarded for a job well done or sleep well knowing you gave everything you had.  To use a sports term, “Leave it all out on the field.”

 

–warren

How to Lose Your Best People

Don’t get discouraged; losing your best people is not as hard as it sounds.  And we’re here to help!  We’ve offered a few good ideas below.  If you have others, please post a comment, and they’ll be added to the list.  Why remain in agony, when the answers are so simple.

#1: Make life easy
That’s right; lavish money, benefits, and perks on your best people.  Foosball, anyone?  They’ll relax from the high-tension goals you’ve set, and things will slowly go undone.  Small things.  Your competitors will make life hard for you, and remove your ability to compensate so graciously.  Your best people will leave as a result.  Harsh realities, but you can pull it off!

#2: Lower your expectations
Why treat your best people like slaves?  They’ve worked hard to get where they are today, and they deserve a rest.  After all, you don’t want to be known as the Pharoah’s taskmaster.  Trust me… this works.  The results will be similar to point #1.  As soon as they realize the company and project goals are negotiable, you won’t have far to go.

#3: Create a Dilbert environment
Don’t know Dilbert?  See the comic to the left, or click here to see the cartoon.  Poor Dilbert is an IT professional who faces more daily incompetence than an Oklahoma Street-sweeper.  (Get it?  Armadillos?  That was my own pitiful attempt at humor.)  🙂  Foster a certain degree of incompetence in the office, and your Dilbert will flee.

#4: Let your projects take care of themselves
They will, you know?  Project management is not a discipline, its a recreation.  Don’t track your project time.  Don’t bother with post-mortem analysis and percent complete.  If you must, use a little spreadsheet with some cool fonts and colors.  Your best people will drift along with you – until their job search pays off.

All kidding aside, people leave for a lot of reasons, and it’s not always the company’s fault.  Don’t beat yourself up too badly.  If you’re trying hard to keep good people, you’re probably doing okay.  It takes a pretty messed up organization to drive good people away.  And sometimes, even the best companies cannot keep them.  Keep up the good work, and don’t let these things happen to you.  🙂

 

–ray

Define: Deadline Date

Deadline: A date associated with a task’s finish date, after which an indicator appears in the ‘Information’ column of Microsoft Project.

 

Microsoft Project allows you to set a deadline date for each task in an MPP project file.  This date is closely linked to the task’s finish date.  See the link below to set a deadline for a task.

http://www.projectteamblog.com/?p=43

 

I prefer deadline dates to task constraints.  They are simple and informal, and do not affect downline task dependancies.  In other words, they simply show a red symbol next to the task rather than affecting the starting dates of other tasks.

 

But honestly, Microsoft Project® is not as elegant as Standard Time® when it comes to time-related things.  It has no timesheet, and cannot accurately track employee hours for tasks.  Obviously, there is an ‘Actual Work’ column, but has no effective way to fill it. Standard Time® is much better suited for that purpose, and it has a task deadline feature as well.

 

–ray